Quadenoord - 16-07-2019

To be able to renovate Landgoed Quadenoord (Renkum) a solar Parc will be installed. For this project Landgoed Quadenoord cooperates with the ValleiEnergie cooperative and with Chint Solar. Chint Solar has a lot of experience and knowledge of developing and building solar parts. Everyone from the environment can participate in this sustainable energy project via the Cooperative Valley Energy. Together with Wageningen University, we are working hard on the biodiversity on the plots. The permit application has been submitted.

Midden-Groningen - 19-06-2019

On Saturday 15 of June the building site of Zonnepark Midden Groningen was open for public. The rainy weather was no reason for the people of Groningen to stay at home. At least 185 interested visitors came to take a look at the largest solar park in the Netherlands under construction.

Midden-Groningen - 28-05-2019

Four months ago we started the construction of Zonnepark Midden Groningen. The work is proceeding according to plan and in the meantime we have installed 98% of the foundation piles and 21% of the solar panels.

Midden-Groningen - 29-04-2019

On Friday the 26th of April Dutch television broadcasted an item about solar parks and solar islands in the Netherlands in a progam called Nieuwsuur (NOS). Zonnepark Midden Groningen was also discussed.

Midden-Groningen - 02-04-2019

At the end of January we started with the construction of Zonnepark Midden Groningen. A lot of work has been done since then. In this article you can read about the work we have done in the past quarter and what we will do next month.

Midden-Groningen - 14-02-2019

On February 13, the construction started of one of the biggest Dutch solar parks of 2019. On November 14th 2018, the Council of State confirmed the environmental permit for the solar park Midden-Groningen.

Midden-Groningen - 18-01-2019

On 21 January, the construction of the Solar Park Midden-Groningen will start. The planned construction period runs from the end of January to October. The first step is to build the fence and the work buildings.

Midden-Groningen - 14-11-2018

The environmental permit for the solar park Midden-Groningen was approved by the Council of State on 14 November. With this ruling from the Administrative Jurisdiction Division, the environmental permit has become irrevocable and the construction can start in the beginning of 2019.

Andijk-Zuid - 07-11-2018

Today, the new solar park in Andijk will be opened by Alderman Nederpelt of the municipality of Medemblik. The park has a capacity of 15 MW and supplies enough renewable energy for 4,622 households, roughly one quarter of all the Medemblik households. In 2017, Chint Solar started the realisation of a solar park with high-efficiency solar panels on a plot of land that was originally allocated as an industrial estate.

Andijk-Zuid - 01-08-2018

Alderman Nederpelt of the municipality of Medemblik has placed the first panel in the Andijk solar park. This summer, a solar park will be built near the business park Andijk Zuid. Chint Solar / Astronergy is the developer of this solar park of approximately 11 hectares, the project has been developed in close collaboration with the VOF Andijk Zuid and the municipality of Medemblik.